FGP Site Construction Compound
As a sub consultant to the project main contractor we were responsible for the early work scope package for main FGP project. The main scope of the early works project was the design of a contractors construction compound with a 600 person PMT building.
Scope for the construction compound:
Layout of the plot for the 3km x 2km site
Design of undergrounds, including the firewater system, potable water, electrical trenches, CCTV/communication trenches and hot water pipelines
Access and service roads
Sanitary drainage system
Site grading and surface water management
Building locations for the firewater pumphouse, canteen, PMT office, training center, warehouses and customs compound
Tank areas with containment bunds
Type 1 high security fencing and security control buildings and gates
Tie-ins to existing utilities, pipelines and services
The project also required the management of sub contracted EPC contractors and the answering of construction RFI’s.